Government secures Sh10.6 billion for Thwake Dam phase 1 completion
Environment & Climate
By
Stephen Rutto
| Sep 02, 2026
Construction works at the Thwake Multipurpose Dam resumed officially on Tuesday after a nearly two-year hiatus, Water Secretary Eng. Samuel A.O. Alima announced.
Speaking during a site visit yesterday, Alima said the government has secured adequate funding from the African Development Bank (AfDB) to complete critical outstanding works.
“Today we are here to witness the resumption of works. " The government has got adequate funds from AfDB, and we expect the Contractor to resume works fully,” he stated.
READ MORE
Inflation jumps to 6.6pc as cost-of-living crisis deepens ahead of 2027 polls
How US state-level pacts seek to unlock US-Kenya trade
Project managers face pressure to build business, leadership skills
Fintech surpasses Sh20b in cross-border transfers as demand for faster digital payments surges
How Nairobi boda boda riders are using collective savings to build businesses
Why State wants union characterised by gross mismanagement liquidated
Why regional growth should begin with one deliberate market choice
Investment fund crosses Sh20b mark after 77pc growth
Kenya Airways acting CEO quits
Kenya tops the world in AI, but do our leaders know that AI drinks water?
According to Alima, the Ministry is keen to ensure the implementation of the three critical items pending, including the completion of the concrete phase, construction of the bridge connecting Makueni and Kitui counties, and the dam gates. The contractor has been directed to operate on a day-and-night schedule.
“The next eight months will be critical,” Alima said. “We have started packaging the downstream works as well. We will be tracking the progress every day.”
Authorities hope to fill the reservoir in a single rainy season, aided by expected El Niño rains, rather than the two seasons originally projected.
“With the Super El Niño, we can finish with one season of rain. We initially expected two seasons. The catchment is big,” Alima noted. He added that the project team is hopeful of completing the filling faster than earlier forecasts.
Alima thanked the leadership and residents of Makueni and Kitui counties for their support. He confirmed that completion of the employer’s camp is underway and that workers are being recalled to the site. A dedicated desk will monitor worker welfare and attendance.
The government has repeatedly announced an allocation of Sh10.6 billion for the project. Alima said sufficient financing and budget have been secured, and the contractor has been instructed to submit a monthly work programme to ensure steady progress and adequate resourcing.
MOST READ
- Inflation jumps to 6.6pc as cost-of-living crisis deepens ahead of 2027 polls
BUSINESS
By Brian Ngugi
- Fintech surpasses Sh20b in cross-border transfers as demand for faster digital payments surges
ENTERPRISE
- Project managers face pressure to build business, leadership skills
ENTERPRISE
By David Njaaga